Sunday, 15 June 2014

Step 6 - the start of the building proper - Casting the foundations


Today is a milestone day as it represents the start of the some real visible construction - Yipeee!

Today we are going to casting zones 1 and 2 of 6 zones of the foundations that we eventually need to construct.




These 2 zones consists of 600 tons of rebar, which we will fill with 2295 m3 of concrete. This is one of the largest single casts in Singapore this year and certainly the largest one I have been involved in, we should be finished in around 16 hours. This is about as exciting as concrete gets!